9. The Main Activities Timetable and Description.

 

Start date

Completion date

Feasibility study:

1/03/2003

30/03/2003

Economic analysis:

1/04/2003

1/05/2003

Financial analysis:

15/04/2003

1/05/2003

Environmental impact assessment:

1/04/2003

1/05/2003

Design studies:

1/03/2003

1/07/2003

Tender documents:

1/08/2003

1/09/2003

Land acquisition:

Not the case

Not the case

Construction:

1/10/2003

1/10/2004

Operational phase:

1/11/2004

 

Please include a summary description and schedule of work.

If earlier phases of the project have already been undertaken, give details.

  

Schedule of work

Months

Design

PUZ, PUD,  SF

Martie 2003

Partnership

SoftVillage  Consortium

Memorandum of understanting with min. 6 local and county administration interested in partnership  SoftVillage Park

April 2003

Licences

Obtinere acorduri, avize, autorizatii , Titlu Parc-MDP

April 2003

Licitatii

Brief Design , Proiect tehnic –executie , Licitatii

July  2003

 

Publicitate , Evaluare, termen contestatii, contracte executie, contracte dirigintie santier (engineer)

+ 6 month

Executie

Predare amplasament, organizare santier

Dec. 2003

E.1

Finalizarea aranjamentelor Contractuale

 ORDIN DE EXECUTIE

Luna 1 , 2004

E.2

Ocuparea locului,utilitati temporare

luna2-luna10

E.3

Pregatirea design-ului detaliat si supravegherea designer-ului

Luna 1-luna110

E.4

Drumuri , SoftVillage _Roads

Luna 1-luna 6

E.5

Constructie noua SoftVillage Office

Luna3,5-luna 10

E.6

Alimentare cu apa, lucrari de incalzire si canalizare

Luna 6,5-luna10

E.7

Instalatie electrica

Luna 6,5-luna10

E.8

Sistem de instalatii de joasa tensiune, curenti slabi)

Luna 7,5-luna 10

E.9

Finisare (faiantare,carpetare etc)

Lun 8-luna10

E.10

Sistem de instalatii exterioare

Luna 5,5-luna10

E.11

Executii in exterior,pavare parcari  si a drumului de acces

Luna5-luna 10

E.12

Testare , anduranta, probe functionale

Luna 9-10

E.13

Inspectia finala si curatenia

Luna 10

E.14

Demolarea obiectelor  temporare, curatenia finala si alte proceduri finale

Luna10

E.15

Receptie finala si derularea procedurilor de garantie post-implementare

Luna 10+ 2 ani.